Meadows of Dan: Quarterly Report—06/30/2004

Route 58 Corridor from Hillsville to Stuart

Quarterly Report

Period

 April 1, 2003 thru June 30, 2004  

Quarterly Report Summary

 This second quarterly report for the project includes activities within the time frame of April 1, 2004 through June 30, 2004.  The project team has been diligently working to ensure this phase of the project meets all requirements of the contract.

All design work, including the roadway and bridge plans, has been submitted, reviewed and approved for construction.

Monthly CPM/Payment Schedule updates are being maintained and transmitted as per the contract.

The minor permit modification, mentioned in the previous quarterly report, has been approved by both the Virginia DEQ and the U.S. Army Corps of Engineers.  Permit obligations such as construction monitoring are on-going and reporting is being submitted to the appropriate agencies.  The project VPDES General Permit expired on June 30, 2004.  Application was made for a new permit and we are in receipt of a new VPDES General Permit for the project.  The effective date of this permit is July 1, 2004 and expires on June 30, 2009.

The project team has increased by adding the following members:  A.H. Harris to supply reinforced geogrid material for the steepened slopes, Adams Construction Company to furnish and install the asphalt pavement, C&P Welding & Steel Erection, Inc. to supply support beams for the shoring for the bridge, E.C. Pace Company to install storm drainage pipe and structures, Iron Ridge Rebar Contractors to install reinforcing steel for the bridge, Painting Solutions to furnish and install the color coating of the concrete for the bridge, Patent Construction Systems to supply the shoring system for the bridge, Resco Steel to supply the reinforcing steel for the bridge, Shelly Foundations, Inc. to install drilled shafts for the bridge, Site-Prep, Inc. of N.C. to perform the soil cement stabilization and Stuart Concrete to supply the transit mix concrete.

Construction activities in Work Area #1 (West End of project to Station 762+50) and Area #2 (Station 762+50 to 780+00 –Blue Ridge Parkway) include completion of mass excavation for mainline west of Rte 600 and new Rte 600 alignment, installation of surface drainage along with fine grading activities for these same areas in preparation of paving activities.  Storm water management basins #1 and #2 have been completed along with the southern portion of the double box culvert.

Construction activities in Work Area #2 (Station 762+50 to 780+00 – Blue Ridge Parkway) include completion of deep drainage pipe and structures and continued mass excavation to either fills or waste area. 

 Construction activities in Work Area #3 (Blue Ridge Parkway Bridge) include completion of detour and traffic switch for Parkway traffic, structure excavation, completion of drilled shafts and start of concrete forming and placement activities for the bridge.

Construction  activities in Work Area #4 (Station 780+00 to East End of project) include completion of deep drainage pipes and structure, completion of storm water management basin #5, continued mass excavation to either fills or waste areas, and start of construction for the single box culvert.

Construction activities in Work Area #5 (Wetlands Compensation Site) include installation of the preliminary erosion control items.

The project is currently on schedule to meet the substantial completion date of December 15, 2005.

Two separate incidents involving damage to power lines to residences occurred during this period.  Neither incident resulted in any substantial damage to property, other than fixing the lines.  Power was restored to the homeowners, in both instances, within several hours.  We have addressed the safety hazards to the work from overhead lines during our project safety meetings and have also installed warning signs at all overhead power line locations within the project limits to further identify and warn of this safety hazard.

There were no material disputes or claims, actions or assertions against Contractor, the Project or Project Right of way, or Lien claims or stop notices file or threatened to be filed by any Person for the period.

The following attachment is a graph depicting the actual cumulative payment applications and the maximum cumulative payments allowed by contract.

Also find attached are project progress photos.

6302004-1

Quarterly Report

Period from April 1, 2004 thru June 30, 2004

Location: West end of Project 0058-070- E02, B601

Date: 7/28/04

Facing Direction: East

6302004-2

Quarterly Report

Period from April 1, 2004 thru June 30, 2004

Location: Double Box Culvert D607     (0058-070- E02, B601)

Date: 7/28/04

Facing Direction: North

6302004-3

Quarterly Report

Period from April 1, 2004 thru June 30, 2004

Location: Blue Ridge Parkway Bridge,  Structure B601 (0058-070- E02, B601)

Date: 7/28/04

Facing Direction: West

6302004-4

Quarterly Report

Period from April 1, 2004 thru June 30, 2004

Location: East end of Project @ Single Box Culvert     (0058-070- E02, B601)

Date: 7/28/04

Facing Direction: East